Spider Project version 10.03 release 139 - from 15.05.2012 |
Pop-up tooltips:
- Tooltips on the buttons in the "Project and Documents" window.
- If a cell value has not enough space to be shown, a tooltip appears with the whole value.
- When the mouse cursor is over a bar in the Gantt diagram, a tooltip appears with information obtained from a template which is set up in the Network diagram.
- New Workplace option - whether to show tooltips in Gantt diagrams.
|
|
Spider Project version 10.03 release 121 - from 11.04.2012 |
- Access rights to the following project tables: Resource Skills, Multi-Resources, Material Sets.
|
|
Spider Project version 10.03 release 119 - from 06.04.2012 |
- Reports and diagrams menu items in Gantt are reorganized in more compact and convenient form.
|
|
Spider Project version 10.03 release 116 - from 2.04.2012 |
- New workplace option "Show links in the fields 'Preceding Activities' and 'Succeeding Activities'".
|
|
Spider Project version 10.03 release 115 - from 30.03.2012 |
- Resource dependencies can be shown in the Activity Network diagram.
- New option of Cost Periods (used by Cost Components, Materials, Resources) - "Percentage of the previous period". It means that Unit Cost of the period is equal to Unit Cost of the previous period plus a percentage of it. This percentage should be entered in the Unit Cost field in this case instead of an absolute number.
|
|
Spider Project version 10.03 release 112 - from 28.03.2012 |
- New field “Critical” in the Links table. The link is supposed to be critical in case it is a main link (i.e. succeeding activities are postponed because of the link) and the succeeding activity is critical.
- All resource dependencies are principal. Thus, it is possible to filter main links in the Links table and display the Resource Critical Path on the Gantt diagram by filtering all links visible in the Links table.
- New Workplace option - "Display main links as bold lines". Affects the Activity Network as well.
- It is possible to select certain color for critical links in the Color Setup Dialog. Affects the Activity Network as well.
- Hierarchical sorting in Gantt diagrams is cancelled.
- New built-in-field “Identifier” in all project tables. It is a unique number for every object. It is increased when a new object is created. Use this field for sorting to see objects creation order.
- Copy the main phase as new project in Project Truncation (where scheduling is unavailable), to get fully-featured project.
|
|
Spider Project version 10.03 release 106 - from 15.03.2012 |
- New calculated column “Preceding link was broken” for activities.
- New calculated column “Broken” for links.
- Recreate Success Probabilities Trends to calculate these columns.
|
|
Spider Project version 10.03 release 102 - from 06.03.2012 |
- It is possible to use working hours of a resource or resource center as EVA report parameter.
- New scheduling option "In case of out of sequence execution". It consists of four items:
- Retained logic
- Retained logic with exception of activities in progress
- Ignore preceding links if activity is in progress
- Ignore preceding links of activities finished
Actually, the two latter items are long-standing settings of Spider scheduling. In previous versions they were selected through the option Ignore preceding activity links if activity is in progress. In case the option was switched on preceding links of activity in progress did not affect the ASAP Start time of the planned remaining part of this activity and the activity started at project Data-Date. In case the option was switched off the activity planned remainder was scheduled according to preceding links, lags of such links were recalculated depending on the activity actual part. Now it is possible to opt for retained logic at scheduling in case some activities have been actually started out of accordance with the approved schedule.
Example:
There are three activities chained successively with Finish-Start links. Due to some reasons the first link was broken, in other words the first activity has not been started, while the second one has been started and thus has certain actual part. The question is when the third activity must be started.
Retained logic provides that the third activity can not be started until the first activity is finished ignoring the second activity finish time; as it was in the approved schedule.
Thus, the abovementioned four scheduling options can be briefly described as:
- Activities in progress are moved to the right in accordance with their preceding links; chain of links after them is totally restored.
- Activities in progress start at project Data-Date, chain of links after them is totally restored.
- Activities in progress start at project Data-Date, chain of links after them is not restored.
- Activities in progress are moved to the right in accordance with their preceding links, chain of links after them is not restored. |
|
Spider Project version 10.03 release 91 - from 17.01.2011 |
Script Language:
- New command OPENFILE - open a file (project, document, execute a script).
- New command PROJTABAPPLYFILTERVALUES - apply filter by values to a project table.
- New command DOCAPPLYFILTERVALUES - apply filter by values to a document.
- New command PROJTABSHOW - show a project table.
- New command DOCSHOW - show a document.
|
|
Spider Project version 10.03 release 90 - from 29.12.2011 |
- It is possible to use cost centers in formulas for cost components. A cost center must contain all the project materials (with expence and income included).
|
|
|
|